Damages
Freight law focus

Delivery delay and carriage obstacles

What to check when delivery is late, access is blocked or the planned carriage cannot continue.

BRANDAUER Rechtsanwälte
Ansprechperson

Mag. Bernhard Brandauer, Rechtsanwalt

BRANDAUER Rechtsanwälte

Orientation on damages matters in Austria.

A delivery delay is more than an uncertain arrival time. Under the CMR, the agreed delivery time matters. If no time was agreed, the relevant question is how long a diligent carrier would reasonably have needed in the circumstances. A carriage obstacle is different: the transport cannot be carried out as described in the consignment note, or delivery cannot take place without further instructions. Examples include a road closure, an unavailable unloading point, a refusal to accept the goods or an unexpected official measure.

This page focuses on the transport event itself. Our pages on carrier liability and cargo damage and consignment notes and documentation cover related issues. The contract, route, goods and communications still need to be examined in each individual case.

Mag. Bernhard Brandauer, Rechtsanwalt

First classification

What happened during the carriage?

Answer three short questions. This first classification cannot replace a review of the transport documents, but it shows which points should be secured first.

01 Question 1

Have the goods reached the agreed delivery place?

A blocked unloading process or a refusal to accept the goods can also be legally relevant.

Ergebnis

Ihre Orientierung

01

The main issue is likely a delivery delay.

Secure the agreed delivery time, the actual chronology and the proven loss. Also check whether a written notice concerning delay compensation must be sent within the CMR time limit.
Classify freight claims and deadlines →
02

There is probably a carriage obstacle.

Document the reason for the obstacle and obtain a clear instruction. Under the CMR, instructions from the person entitled to dispose of the goods may be required before arrival; after arrival, the consignor is generally involved.
Review the CMR and transport contract →
03

The obstacle has arisen at the delivery place.

Record when and why acceptance or unloading was impossible. The CMR contains specific rules for these situations, which must be distinguished from an ordinary delay.
Review shipment documents →
Two situations, different first steps

Delivery delay or carriage obstacle?

Both situations may occur together, but they raise different practical questions.

Delivery delay or carriage obstacle?
Question Delivery delay Carriage obstacle
What happened? The goods were not delivered within the agreed or reasonable time. The agreed carriage or delivery is impossible because of an obstacle.
What should be clarified first? The delivery time, actual duration and cause of the delay. Who may give instructions and which solution protects that person’s interests?
Which documents matter? Order, consignment note, delivery slot, tracking, arrival time and loss calculation. Consignment note, obstacle notice, photographs, messages, instructions, storage and unloading costs.
Which CMR rules are central? Article 19 on delay and Article 23(5) on compensation for delay. Articles 14 to 16 on instructions, unloading, custody and further measures.

The actual claim depends on the applicable transport law, contract and type of loss.

When a delivery delay exists under the CMR

Article 19 CMR defines delay by reference to the agreed delivery time. If no time was agreed, the duration is assessed against what a diligent carrier could reasonably have required in the circumstances. For partial loads, the normal time needed to assemble a complete load is also relevant.

Section 429 of the Austrian Commercial Code likewise addresses damage caused by failure to meet the delivery time. The carrier is not liable under that rule where the delay resulted from circumstances that an ordinary carrier could not prevent. This is not a blanket release. The cause, foreseeability, available responses and actual care must be examined.

  • A non-binding preferred time is not automatically an agreed delivery deadline.
  • A delivery window can be established by the order, consignment note, email or established practice.
  • A delay may matter even if the goods eventually arrive complete.
  • For combined transport, the responsibility of each participant must be separated.

Carriage obstacles before and at the destination

Article 14 CMR addresses a situation in which the carriage can no longer be performed according to the consignment note before the destination is reached. The carrier must generally request instructions from the person entitled to dispose of the goods. If a different performance is possible but instructions cannot be obtained in reasonable time, the carrier must take steps that reasonably protect that person’s interests.

If the problem arises at the delivery place, for example because the consignee refuses the goods or unloading is unavailable, Article 15 CMR becomes relevant. The consignor is involved. Article 16 CMR deals with costs, unloading and custody. For perishable goods or disproportionate storage costs, a sale may also be possible. The reason, communication and proportionality of the decision should be recorded carefully.

  • A road closure, accident, customs problem, missing access and refusal to accept goods are not automatically the same situation.
  • A telephone instruction should be confirmed in writing immediately.
  • An alternative unloading place, transshipment or storage needs a traceable basis.
  • Waiting time and additional costs should be recorded with start, end and cause.

Liability and loss caused by late delivery

Late delivery does not automatically justify every claimed consequential loss. Under Article 23(5) CMR, the claimant must prove that the delay caused the loss. Compensation is generally limited to the amount of the carriage charge. A higher amount may be available where a special interest in delivery was validly declared under Article 26 CMR.

The issue is therefore not just the invoices. Causation must be shown. Did the loss result from the late delivery? Would it have occurred even with timely delivery? Could a reasonable substitute measure have reduced it? For perishable goods, production interruptions, contractual penalties or missed delivery windows, the factual sequence and contractual basis should be reviewed together.

The CMR liability check should be kept separate from the documentation of cargo damage. Loss or damage raises different evidence questions from a delay without physical damage.

Notices and reservations that need to be preserved

An internal note about the delay is not enough. Article 30(3) CMR provides that compensation for delay is not payable unless a written reservation is sent within 21 days from the time the goods were placed at the disposal of the consignee. Proof of receipt should be retained.

The reservation should clearly identify the transport and the delay. It should include the consignment note number, agreed delivery time, actual time of availability, a short description of the loss and an express reservation of delay damages. The exact amount can follow if the reservation is timely and clear.

Apparent and concealed cargo damage follows different rules under Article 30 CMR. The inspection at delivery and the written notices for non-apparent damage should therefore not be confused with the reservation for delay.

Evidence for cause, instructions and the amount of loss

In practice, the chronology often decides the case. Preserve the order, consignment note, delivery time, booked slot, tracking data and all messages between consignor, carrier, forwarder and consignee. For an obstacle, add photographs, official notices, accident records and the instruction that was given.

The loss calculation should explain each item and why it resulted from the delay or obstacle. This can include additional storage, transshipment, return transport, unproductive waiting time, replacement carriage or proven production consequences. A single unitemised total makes the assessment harder.

Use the shipment documents checklist for the initial collection. It does not replace legal advice, but it helps prevent the loss of essential timestamps and instructions.

  • Consignment note and transport order with all agreed times
  • Tracking, GPS, timestamps and documented arrival
  • Obstacle notice with place, time, cause and contact person
  • Written instructions and confirmation of the measures taken
  • Invoices, storage records, additional freight and a concrete loss calculation

Limitation periods and the right response

Under Article 32 CMR, an action arising from carriage is generally subject to a one-year limitation period. The period is three years in cases of wilful misconduct or equivalent default. The starting point depends on the claim. For delay, it generally begins on the day of delivery. A written claim can suspend the period under the conditions of Article 32 CMR until the carrier rejects it in writing and returns the documents.

This is not a substitute for a deadline review. It must first be established whether the CMR applies, who is entitled to claim and whether a carrier, forwarder, consignor or consignee is involved in another legal capacity. Domestic carriage or special contractual terms may require a different analysis.

Contact us with the consignment note, transport order, first obstacle or delay notice and a short chronology. This makes it possible to identify quickly which instruction, reservation and next step matter most.

Frequently asked questions

Questions often asked about delay and carriage obstacles

What is the difference between a delivery delay and a carriage obstacle? +
A delivery delay concerns the agreed or reasonable delivery time being exceeded. A carriage obstacle means that performance or delivery under the consignment note is impossible or requires instructions. Both can occur at the same time.
Does the carrier have to return immediately when an obstacle arises? +
Not automatically. Under the CMR, the carrier must first consider the person entitled to give instructions and the available solutions. If instructions cannot be obtained in time, the carrier must act reasonably in that person’s interests.
Can I claim compensation for a delivery delay? +
Possibly, but the claimant generally has to prove the loss caused by the delay and comply with the CMR requirements. Article 23(5) CMR generally limits compensation to the carriage charge, subject to specific exceptions.
What time limit applies to a reservation for delay? +
For a CMR carriage, a written reservation for delay compensation generally has to be sent within 21 days from the time the goods were placed at the consignee’s disposal. Proof of receipt should be kept.
What should I record when access to the delivery site is blocked? +
Record place and time, the reason for the closure, photographs or official notices, communications with the carrier and every instruction. Waiting time, transshipment, storage and other costs should be listed separately.
Who pays additional costs after a carriage obstacle? +
That depends on the cause, contract, instruction and applicable law. The CMR contains specific rules for instructions and follow-up measures. The documents are needed before the cost burden can be allocated.
How long can a CMR claim be pursued? +
Article 32 CMR generally provides for one year, or three years for wilful misconduct or equivalent default. The starting point and the effect of a written claim must be checked for the particular claim.

Sources

BRANDaktuelle Legal News

Subscribe to legal news

Receive new articles and legal information from the firm with BRANDaktuelle Legal News.

Subscribe to the newsletter

Delivery delay or carriage obstacle?

We review the consignment note, chronology, instructions and loss documents with you. Contact us so that the next steps are clear in time.

Kontakt

Discuss your matter

Adresse

BRANDAUER Rechtsanwälte GmbH Giselakai 51 5020 Salzburg